Two numbers, and they are nothing like each other. The application fee is a fixed scale fee, charged by lot size. The premium is a share of what the land is worth once it carries the new category, and on a real plot that is six or seven figures.
Which share depends on light, medium or heavy industry. Selangor publishes different rates for each, rising in that order. The classification follows the operation you intend to run, so the same plot carries a different premium depending on what you put on it.
The zoning decides it before the land office does. A council shall not grant planning permission for development that contravenes the local plan. Not may refuse. Shall not grant.
And approval is not conversion. The change takes effect when it is endorsed on the title, not when the letter arrives.
The two numbers, and almost nobody separates them
Ask what it costs to convert agricultural land to industrial land in Selangor and you will be given one figure. There are two, they do different jobs, and the gap between them is the whole subject.
The application fee is prescribed in the Selangor Land Rules and listed on the district land office checklist. Not more than one hectare, RM70. One to ten hectares, RM140. Above ten hectares, RM100 for the first ten plus RM10 for each further hectare. Amending an express condition, RM60. Selangor's own e-Tanah guide shows the online submission payment as RM60.
That is the cost of asking. It is the same whether the answer is yes or no.
The premium is the price of the change itself. It is assessed after approval, against what the land is worth once it carries the new category, and it is demanded by a formal notice rather than paid at submission. On a plot of any size it is a six or seven figure number.
So when a forum reply says conversion costs a couple of hundred ringgit, it is not wrong about the fee. It has simply left out the part that decides whether the deal works.
What the rate depends on: light, medium or heavy
Here is the part no guide I have read explains, and it is the part an occupier can actually plan around.
The premium is not one rate for industrial land. Selangor has published separate rates for light, medium and heavy industry, rising in that order. Which one applies follows the class of industry the land is being converted for, and that follows the operation you intend to run in the building.
So two identical plots, side by side, same size, same road, can carry materially different premiums because one buyer is assembling electronics and the other is doing hot work. The land did not change. The intended use did.
That matters commercially in a way the published guides miss entirely. If your process sits near a classification boundary, the classification is a number in your acquisition model, not an administrative detail to be sorted out later. It is worth establishing which class your operation falls into before you price the land, because it moves the premium by a third.
What Selangor has published, and how old it is
I am going to give you the rates, and then tell you exactly how much to trust them, because the second part is more useful than the first.
| Conversion | Rate quoted | Where it comes from |
|---|---|---|
| Agriculture to light industry | 20 per cent | Pejabat Tanah dan Galian Selangor, on a page whose own last update is November 2015. The same three figures appear in a 2016 property article and on two undated agency sites. |
| Agriculture to medium industry | 25 per cent | |
| Agriculture to heavy industry | 30 per cent |
The percentage is applied to the land value as assessed by the valuation department, not to what you paid for it.
Now the caveat, and please take it seriously. Four sources agree on those three numbers, which is reassuring, and every one of them is at least nine years old or undated. Agreement between old sources is not currency. Selangor sets rates of this kind by circular from the Director of Land and Mines, those circulars are indexed by year on the state land office site, and I could not obtain the current one.
So treat 20, 25 and 30 as an order of magnitude for your first model, and get the live figure from the district land office before anything depends on it. That single phone call is worth more than every percentage published on the internet, this page included.
What you are actually changing is the category
Worth being precise, because the words get used loosely. You are not converting the land. You are varying what the title says about it.
There are three categories of land use, and commercial is not one of them. Agriculture, building and industry. A conversion from agriculture to industry moves the entry on that line, and in the same order it can rescind or amend the express conditions, and rescind, amend or impose a restriction in interest.
The statutory form that records it lists exactly what can be done: vary a category from one to another, impose a category where none exists, rescind an express condition, rescind a land use descriptor such as Padi, Getah or Kampung, amend conditions, impose new ones, and deal with restrictions in interest.
Two consequences people miss. Express conditions do not simply fall away when the category changes; they are separately dealt with in the same order, and new ones are usually imposed. And the form carries a field for a new quit rent, so a reassessment is part of the order rather than something that arrives later.
Section 124, 124A or 204D: three different instruments
These are mixed up constantly, including on sites selling industrial land, so it is worth thirty seconds.
- Section 124, Form 7C. Varies conditions, restrictions and categories on a title as it stands. The title survives. This is a plain tukar syarat on one whole lot
- Section 124A, Form 7D. Headed, in the statutory form itself, in respect of proposed sub-divisional portions of land. You are subdividing and asking for a different category on the resulting pieces at the same time. It is not a form for contiguous lots and it is not the general conversion form
- Section 204D, Form 12D. Surrender and re-alienation. The title is cancelled and new ones issue. This is what a scheme needs when lot boundaries have to be re-cut or road and drainage reserves excised, and it requires a layout plan approved by the local authority
If you are converting one whole lot and not cutting it up, your form is 7C. I mention it because 7D is quoted as the conversion form in several places it should not be, and because a form number is the kind of detail that tells you quickly whether a source has actually looked.
Which instrument a particular scheme needs is a question for a land lawyer on your facts. The distinction to carry away is structural: section 124 edits a title, section 204D replaces it.
The zoning decides it before the land office does
This is the first thing to check and the cheapest, and it is the one that most often makes the rest academic.
Section 19(1) of the Town and Country Planning Act 1976 says nobody other than a local authority may commence or carry out any development without planning permission. Section 22(2)(a) says the authority shall take the development plan into consideration. And section 22(4)(a) says the authority shall not grant planning permission where the development would contravene a provision of the development plan.
Read that again. Not may refuse. Shall not grant.
The development plan means the local plan, or the structure plan where no local plan exists. So if the local plan does not zone your lot for industry, the council is not permitted to approve industrial development on it, and the conversion question never gets a chance to arise.
Which is why the order of work starts at the planning department and not the land office. A copy of the local plan and ten minutes with the zoning map costs nothing and settles the only question that can end the exercise outright.
One more number from the same Act. Planning permission lapses after twelve months if development has not commenced, and development without permission is an offence carrying a fine of up to RM500,000, up to two years, or both, with daily fines while it continues, and the landowner is deemed to have permitted it.
Approval is not conversion. The endorsement is.
If you take one thing from this page, take this one, because it is the most expensive mistake available and it happens to people who did everything else right.
The variation takes effect when it is endorsed on the title. Not when the approval letter arrives. Not when the premium is paid. The Federal Court has held that a tenancy granted for a use the title did not yet permit was illegal and void, notwithstanding that approval had been given.
So there is a window, and it can be a long one, in which you have an approval in your file, a receipt for a very large premium, and a title that still says agriculture. During that window the land is agricultural land in law. A lease for industrial use signed in that window is a lease for a use the register does not allow.
The practical instruction is short. Ask your solicitor to confirm the endorsement is on the title before any tenancy is signed, and do not accept the approval letter as evidence that it is. It is evidence of a decision, not of a change.
And the exposure runs the other way too. Breach of an express condition is a continuing breach, and land in breach is liable to forfeiture. That is not a fine. That is the land.
What the application actually has to contain
From a Selangor district land office checklist for an application under section 124, so this is the real list rather than a general one:
- The application on the prescribed schedule to the Selangor Land Rules, in duplicate
- Ten copies of the key plan and location plan, prepared and signed by a registered Associate Town Planner
- A development proposal report to the planning department's guidelines, with two extra copies where the purpose is industrial
- The original official search certificate on the title
- The current quit rent receipt, and all quit rent paid in full
- Written consent from any chargee or caveator
- Technical comments from the local council, the planning department, the drainage and irrigation department and the environment department
Three things worth drawing out of that list. It needs a registered town planner, so there is a professional fee before you have asked anybody anything. It needs technical comments from four agencies, which is where the calendar goes. And the whole thing must be for a whole lot: a variation under section 124 applies to the entire title, not to part of it.
The clocks, and what runs out
Three time limits that are real and that catch people who treat an approval as something that keeps.
- Technical comments expire after twelve months. Collected too early and the application stalls, they have to be refreshed
- Planning permission lapses after twelve months if development has not commenced
- The approval itself carries a compliance period. Approval under section 124A is expressly conditional on compliance within a period the State Authority specifies. Non-compliance is a continuing breach and the land becomes liable to forfeiture
What Selangor does not publish, as far as I can find, is a committed processing time for the application itself. The figures circulating in the market run from several months to two years depending on who is counting and from when they start. I am not going to add another number to that pile.
What is not published, and what to ask instead
Most articles on this subject end by sounding confident. This one ends by telling you where the information actually runs out, because knowing that is worth more than a confident guess.
Things I could not establish from a current official source, and which you should therefore ask the district land office rather than read anywhere:
- The current premium rate for agriculture to industry in Selangor, and the circular number that sets it
- The committed processing time, if there is one
- Whether every case goes to the state executive council or some are delegated
- The standard compliance period written into a Selangor approval
- Whether a lender will advance against land pending conversion, which is a commercial question nobody online seems to answer and which decides a lot of deals
Whether a particular application will be approved is a different kind of question again, and not one I am going to answer. Reasons for refusal are not published, and whether to give them is discretionary. Anyone who tells you confidently that your lot will be approved is guessing with your money.
What I would check before paying for anything
In this order, and the first three cost nothing:
- The local plan zoning for the lot. If it is not zoned for industry, stop here. The council is not permitted to approve it
- The title. Category, express conditions, any restriction in interest, and whether it is a pre-1966 title with no category at all
- Which class of industry your intended operation falls into. Light, medium and heavy are different premiums, and it is a number in the model, not a detail for later
- The current premium rate, from the district land office, with the date you were told it
- Quit rent, both paid up and what it becomes afterwards
- And a conveyancing solicitor, before the sale and purchase agreement is drafted, not after
The thread running through all of it is the same one that runs through everything else on this site. The building is not what decides. The title decides, and the title is a document you can read before you spend anything.
Related
- Versi Bahasa Melayu artikel ini: Premium bukan yuran, ia peratusan daripada nilai tanah
- Industrial, commercial or residential: what your title actually permits, the three categories and the two words that are not among them
- Terrace, Semi-D, Detached: what counts as industrial property, the category on the title and the six shapes
- Leasehold or freehold? Check the geran, not the flyer, including the restriction in interest line
- Can a foreigner buy industrial property in Malaysia?, where state consent is a second approval on top
- The mezzanine nobody approved, what happens when the building and the approvals disagree
- CF or CCC? What it means for a factory, warehouse or shop lot
- psf on land or psf on built-up?, which basis a premium percentage is working from
- Versi Bahasa Melayu: Kategori kegunaan tanah
Frequently asked questions
How much does it cost to convert agricultural land to industrial land in Selangor?
There are two separate numbers and they are nothing like each other. The application fee is a fixed scale fee set by the Selangor Land Rules and charged by lot size: at the time of writing RM70 for up to one hectare and RM140 for one to ten hectares, with a formula above that. The premium is a percentage of what the land is worth, assessed by the valuation department, and on a sizeable plot it runs to six or seven figures. If somebody quotes you a conversion cost in the hundreds of ringgit, they have quoted the filing fee and left out the part that matters.
What is the difference between the application fee and the premium?
The fee buys you a decision. The premium buys you the change in category. The fee is prescribed in the Selangor Land Rules, is payable on submission, and is the same whether the answer is yes or no. The premium is assessed after approval and demanded by a formal notice, and it reflects the uplift in value that the new category creates. One is administration, the other is the price of the uplift.
What decides whether the premium rate is 20, 25 or 30 per cent?
Which class of industry the land is being converted for. Selangor has published separate rates for light, medium and heavy industry, rising in that order. This is the part almost no guide explains, and it is the part an occupier can actually plan around, because the classification follows what you intend to do in the building. The same plot carries a different premium depending on the operation you put on it.
Are the Selangor premium rates published anywhere current?
Not that I can find. The rates quoted everywhere, including on this page, trace back to a Pejabat Tanah dan Galian Selangor page whose own last update is November 2015, and to a 2016 property article. They agree with each other, which is reassuring, but agreement between old sources is not currency. Selangor publishes rates of this kind by circular from the Director of Land and Mines, and I could not obtain the current circular. Treat every percentage you read, here included, as an order of magnitude and get the figure from the land office.
Do I need planning permission before I apply to convert?
Not as a matter of land law, and this surprises people. The statutory form for a simultaneous subdivision and conversion expressly asks for the planning authority's approval if one has been given, which means the land application can be decided before planning permission exists. In practice in Selangor the two run together through the One Stop Centre. But the zoning question comes first in substance whatever the paperwork order, for the reason in the next answer.
Can the council refuse planning permission because of the local plan?
It must. Section 22(4)(a) of the Town and Country Planning Act 1976 says the local planning authority shall not grant permission where the development would contravene a provision of the development plan. Not may refuse. Shall not grant. So if the local plan does not zone your lot for industry, the conversion question never arises, and checking the plan is the first thing to do and the cheapest.
What is Form 7C and what is Form 7D?
Two different applications and they are routinely mixed up. Form 7C is the application under section 124 of the National Land Code, which varies the conditions, restrictions or category on a title as it stands. Form 7D is the application under section 124A, which is for proposed sub-divisional portions: you are subdividing and asking for a different category on the resulting pieces at the same time. If you are converting one whole lot and not cutting it up, your form is 7C.
What is the difference between tukar syarat and surrender and re-alienation?
Tukar syarat under section 124 varies what the existing title says and the title survives. Surrender and re-alienation under section 204D cancels the title and issues new ones, which is what a scheme needs when lot boundaries have to be re-cut or road and drainage reserves excised. The second is a bigger, slower instrument. Which one a particular scheme needs is a question for a land lawyer on the facts, not something to infer from a website.
When does the conversion actually take effect?
On endorsement of the variation on the title. Not on the approval letter and not on payment of the premium. The Federal Court has held that a tenancy granted for a use the title did not yet permit was illegal and void, even though approval had been given. Until the register says industry, the land is still agricultural land in law, whatever is in your file.
Can I lease the building out once approval is given?
This is exactly the trap in the answer above, and it is the most expensive mistake on this page. Approval is not the change. Until the endorsement is on the title, a lease for an industrial use is a lease for a use the title does not permit. Ask your solicitor to confirm the endorsement is done before any tenancy is signed, and do not accept an approval letter as evidence that it is.
How long does the whole thing take?
Selangor does not publish a committed processing time for this that I could find, and the figures circulating in the market range from several months to two years depending on who is counting and from when. Two clocks you can rely on: technical department comments supporting the application go stale after twelve months, and a planning permission lapses after twelve months if development has not commenced. Both are statutory, both are real, and both have caught people who treated an approval as something that keeps.
Does my quit rent change after conversion?
Yes. The statutory form that records the variation carries a field for the new quit rent alongside the payment, so a reassessment is part of the order itself rather than something that follows later. Industrial quit rent is not agricultural quit rent, and it is a recurring cost that should be in the model before you buy, not discovered on the first bill.
References
- Laws of Malaysia, Attorney General's Chambers. Search for the National Land Code and read sections 52, 124, 124A and 204D. Note that I was not able to open this from my own machine, so I am sending you to the source rather than quoting it as read
- Pejabat Tanah dan Galian Selangor. The state land office, and the only place to get the current premium rate and the circular that sets it. Its own circulars are indexed by year
- e-Tanah Selangor, where applications under section 124 have been submitted since October 2023, and where the user guide for the process is published
- Jabatan Perancangan Bandar dan Desa Selangor, for the local plan, the zoning, and the planning permission procedure. Start here, not at the land office
- Town and Country Planning Act 1976 (Act 172), PDF. Sections 19, 22, 24 and 26 are the ones quoted here. Hosted by Penang's planning department, and it is the same federal Act
- Statutory Form 7C, section 124 and Form 7D, section 124A, PDFs. These are the National Land Code forms, the same in every state. Read the headings and the 7C against 7D question answers itself
- Selangor Land Rules 2003, which prescribe the application fees and the schedule the application is made on. Quoted here from a Selangor district land office checklist rather than from the Rules themselves
Note on this article. It describes a process in general terms, for industrial land in Selangor, as at 8 October 2026. No specific property, lot, price or application is being described, and the photographs are my own, cropped so that no building, business, person or vehicle is identifiable. The premium percentages are reported from sources that are at least nine years old or undated, and are given as an order of magnitude only. Get the current figure from the district land office. I am not a lawyer, a licensed valuer or a town planner. Whether a particular lot will be approved, on what conditions, and at what premium, are questions for those professionals and for the land office, and nothing here is legal, planning, valuation, financial or tax advice.